Accessibility Projects:
The work is 90% complete. The elevator hoist way,equipment and cab are installed. The new entrance doors, windows are completed. The canopy work is in progress.
The concrete work for the accessible ramp is complete. The metal railing installation is in progress. Also, Phase Two Electrical Work is complete.
Metal panels for the elevator shaft and wall tile at elevator entrance will be installed in the next (3) weeks.
The elevator cab flooring installation is ongoing.
The elevator balancing leveling is scheduled for the end of October.
The DOB elevator inspection is pending.
Facades Projects: Facade projects are ongoing this Fall.
The work is 90% complete. North, East, and South pipe scaffolds are demobilized. The sidewalk shed on the East Elevation is complete. West Elevation is about 92% complete. The soil side of the wall has been excavated for the North Elevation Retaining Wall.
Work is approximately 99% complete overall.
We are awaiting the final engineer’s report to start removal of the bridging.
The anticipated completion of the work is at the end of October.
When completed, the new ARC will be a major upgrade of the 50+ year-old structure – a modern, accessible, Code-compliant facility comprised of a new entrance Lobby, gender-flexible Locker Rooms for home and visiting teams, Team, Training, and Equipment Storage Rooms, Coach’s Offices and Conference Room, and All-Gender Restrooms. HVAC, Electrical, Plumbing and Fire Protection systems were replaced throughout. New furniture, lockers, and IT, AV and security systems are provided, as well.
Status: The schedule provided by the Construction Manager indicates the end of October turnover to Pratt.
Bathrooms, lockers and training facilities are 90% complete. Accessible entrance doors, new lobby and turnstiles are scheduled for October.
Millwork and bathroom partitions are ongoing. HVAC testing and balancing in progress.
The ISC is undergoing a partial gut renovation to become the new home for Counseling, Learning Access, Student Advocacy, Health Services and Student Affairs. Designed by FXCollaborative, Turner Construction has been hired as the Construction Manager for the project. The scope of work includes new testing rooms, a medical floor, counseling and conference rooms, a food pantry and Student Affairs suite. Once completed, the building will be a hub for the health and wellbeing of the Pratt community.
Turner Construction has been engaged for pre-construction services and is actively working on procuring long-lead items. In the next few weeks, the building will be enclosed with a site fence in preparation for work to begin. Concurrently, the construction documentation has recently been completed by the design team led by FXCollaboration.
In the coming weeks, the contractor will begin to construct perimeter fencing around the building.
Please adhere to all signage for safety and temporary closures. Thank you for your cooperation as we continue improvements to the Campus.
For the latest update regarding the work requests, please refer to the 2024 Master Conditions Report. Submit a work order here.Contact Office of Facilities Management at facility@pratt.edu or (718) 636-3579.
Final training and adjustments on the East Hall Boiler Plant continue; the boilers and infrastructure have been completed.
Due to work on the Plaza landscape and sitework improvements, the building is not accessible from Grand Avenue. As an alternative, the building is accessible from the courtyard side of East Hall.
The work consists of new seating with trees, plants and lighting. The Project is approximately 95% completed. A new sidewalk has been constructed on the Grand Ave along the Plaza.
The planter and trees have been installed. The pavers are being installed and the canopy and work tables are under construction.
The project is expected to be completed in August 2024.
In the next few weeks, scaffolding will be erected to start the facade restoration project on the courtyard side of East Hall. It will be noisy and dusty at times. We will continue to provide updates on the project timeline.
The East Hall is not accessible from Grand Avenue. As an alternative, the building is accessible from the courtyard side.
Please see below for a bird’s eye view of Plaza work courtesy JRM Construction Management. Also included below are photos of landscaping and plaza progress photos.
Accessibility Projects:
Installation of the new elevator and Ryerson entrance are ongoing.
The elevator shaft and exterior wall have been constructed. The new stairs and ramp leading to the new elevator lobby will begin in the next few weeks.
Expected Completion is the end of September 2024. The elevator will be available for public use post NYC Department of Buildings elevator inspection approval.
Ryerson Gate is temporarily closed due to construction. As an alternative, please enter via the main entrance gate at 200 Willoughby Ave. There is an accessible entrance on Grand Ave to North Hall.
FISP facade repairs are underway.
Scaffolding has been erected along the facade.
Expected completion is Winter 2024.
Please adhere to signage posted for safety.
Progress Photo of ELJ Hall scaffolding below.
Phase 3, exterior facade and window repairs are underway.
The final phase of the work began this Summer. Repairs to the rear of the building will continue into the Fall.
Repairs to the rear of the building will continue until the Fall.
Completion is expected by September 2024.
The installation of the new custom windows in both Machinery and Chemistry Buildings continues this Summer and into Fall 2024.
The new windows will be double pain and thermal. Replacements continue at both locations including installation.
The windows were designed to match the original as closely as possible to maintain the 1900’s character.
Expected completion is August 2024.
Facilities are working with the departments in both Machinery and Chemistry Buildings to coordinate the installation schedule.
See below for Progress Photos of Machinery & Engineering Building Window Replacement Project
Willoughby Residence Hall Interior renovations continue this summer for 3 additional floors (12, 14 & 15). Work included new finishes to interior walls, ceiling, flooring, lighting, new bedroom doors, appliances and bathroom renovations. Upgrades to corridor lighting, carpeting and apartment doors were also part of the interior renovations.
Expected Completion is August 2024.
Access to the 12th, 14th and 15th floor will be restricted temporarily until completion of the renovation.
See below for Progress Photos of 215 Willoughby Residence Hall Renovation.
Project scope includes a complete gut-renovation/ replacement of the gym-level locker rooms, athletic facilities and restrooms. Work is under construction, with partitions and infrastructure upgrades nearing completion, and finish work underway.
The schedule provided by the Construction Manager, Richter+Ratner indicates a mid-October turnover to Pratt.
When completed, the new ARC will be a major upgrade of the 50+ year-old structure – a modern, accessible, Code-compliant facility comprised of a new entrance Lobby, gender-flexible Locker Rooms for home and visiting teams, Team, Training, and Equipment Storage Rooms, Coach’s Offices and Conference Room, and All-Gender Restrooms. HVAC, Electrical, Plumbing and Fire Protection systems were replaced throughout. New furniture, lockers, and IT, AV and security systems are provided, as well.
Please adhere to all signage for safety and temporary closures. Thank you for your cooperation as we continue improvements to the Campus.
For the latest update regarding the work requests, please refer to the 2024 Master Conditions Report.Contact Office of Facilities Management at facility@pratt.edu or (718) 636-3579.
Substantial Completion for Boiler Scope – Dec 2023
Plaza Landscape Completion – Spring 2024
Project Team: Burns; Jacobs Wyper; SCAPE; JRM Construction
The boiler plant project is a complete gut renovation upgrading the existing centralized steam generating and distribution system to new high efficiency boilers. Decommissioning the two 1940’s boilers and one defunct/out of service boiler. This work will install 2 new high pressure steam boilers that can be converted to low pressure steam in the future when the outer buildings are removed from campus steam and converted to clean energy for heating and cooling. The plaza had severe structural damage and corrosion to the existing columns and beams and was considered unsafe. The smoke stack and facade require structural repairs and repointing – the stack was restored to its original height. In addition to a new steam plant, the project features a new plaza including landscaping and seating.
Construction – Summer 2023
Project Team: Napach Architecture; L+M Construction
Continued effort to refresh each floor (approx 17,000 sf per floor / 70,000 sf) – total of 16 floors (there is a floor 17 but no 13th floor). Also renovating one line of bathrooms (7 and 8 line). Next summer (2024) 2 floors 12 + 14 leaving floors 15,16,17 unrenovated.
Construction Completion – December 2023
Project Team: Jacobs Wyper; McGowan
The building houses most of Pratt’s General Purpose Classrooms; the Writing Center; the Provost’s Office; and Creative Arts Therapy (including two dance studios with sprung floors) – which are all currently inaccessible spaces – this project will create a fully accessible building.
Construction Completion – November 2023
Project Team: L&M Construction
Upgrade to all classrooms furniture, finishes and equipment throughout the building that includes Floors 1, 2 and 3.
Construction Completion – November 2023
Project Team: MAD Architecture; Talisen Construction (windows); Sasaski (programming study for restack)
The CME complex is a historic structure with very little renovation over the years. It ranks high on Pratt’s energy masterplan and suffers from decades of deferred maintenance. The complex houses all of Fine Arts shops (printmaking; ceramics/kilns; jewelry; metal /welding shop; and wood shop, Fine Arts drawing studios, and the Fine Arts senior sculpture studios. In addition to Fine Arts, the complex also houses the Schafler Gallery; IT computer and production labs; the Sustainability Center; General Use Classrooms; the Materials Lab and plaster studios for the School of Design. The complex needs an electrical upgrade and new mechanical systems to take the building off campus steam and remove the inefficient window AC units. The windows were recently replaced in the Chemistry wing – replacement of the existing single pane windows in Machinery + Engineering will begin this summer. Preplanning began in the Spring for “restacking” the Engineering, Machinery, and Chemistry (EMC) complex to update the Undergraduate Fine Arts (UG Fine Arts). This effort will focus on the following areas:
Confirm and evaluate the use of the EMC complex to support UG Fine Arts Update the space utilization study and program statement for UG Fine Arts and IT departments, both of which will be located in the facility
Evaluate the functionality of general use classroom space in the EMC complex Develop design concept(s) to accommodate UG Fine Arts in the EMC complex
Construction Completion – August 2023
Project Team: BA Global
Renovations to the existing bathrooms located on the East side of Pantas Hall. The construction includes the removal of existing bathroom fixtures, installation of new sinks, showers, toilets, accessories, tiles, painting, plumbing and electrical in the Eastside wing of the residence hall. The work includes 28 bathrooms located on 8 floors. Last year renovations were completed for the West side bathrooms.
Construction Completion – August 2023
Project Team: SJS Construction
Accessibility upgrades to the existing terrace through installation of a new ADA compliant ramp. The patio pavement and surrounding landscape will be renovated to improve the overall space. This includes installation of new bollards, fences, pavers, planter edging, and security swipe access.
Other projects ongoing and future projects include:
Project | Completion |
---|---|
East Hall Facade Repair | Fall 2023 |
Main Building Facade Restoration | October 2023 |
Higgins Hall Facade Restoration | November 2023 |
100 Grand Facade Restoration | October 2023 |
Higgins Hall Lower Level – Student Lounge | Summer 2023 |
Work continues on the new East Plaza Deck above the Boiler Room. During the next few weeks the contractor will continue to install the structural steel for the new plaza deck over phase 2 & 3. The interior chimney repairs are ongoing with completion scheduled for the end of April.
Work within the boiler room in preparation for the new boilers is progressing. New concrete basement slab, steam piping and mechanical equipment installation continues through the end of May. The new boilers will arrive in early June.
Foot traffic around the plaza and into East Hall is redirected during this time. Facilities Management staff along with the construction manager will be monitoring the work. We will notify the campus if there are any changes to the schedule. Please expect periodic noise during performance of the work.
Other projects scheduled to begin this Spring are:
- East Hall and Main building masonry repairs and repointing.
- Engineering and Machinery Window Replacement.
- North Hall Accessibility upgrade and Elevator Project.
- Pratt Studios Fire Escape Renovations.
Please adhere to all signage for safety and temporary closures. Thank you for your cooperation as we continue improvements to the Campus.
Contact Office of Facilities Management at facility@pratt.edu or (718) 636-3579.
This is to inform the campus of the ongoing upgrades to the boilers and creation of a new plaza above the boiler plant along Grand Avenue.
- Phase 2 plaza concrete deck and steel removal will begin in early March. Prep work has begun for the demolition of the concrete slab. Work is expected to be completed by the end of the month. It is similar to the work that took place on Phase 1 in the Fall.
- The work of removing the concrete slab and steel will be noisy periodically throughout the course of the demolition. We are working with the contractor to help minimize the disruptions.
- Once the work commences it is expected to take 10-14 days to complete.
- Other updates; Phase 1 work is nearing completion: structural steel, columns and new footings are installed in preparation for the new plaza deck. Chimney repairs are ongoing to restore the interior and exterior brickwork. As part of the repairs the chimney stack will be restored to the original 1887 height.
East Hall Plaza
- The reimaged plaza in front of East Hall is designed by Scape Landscape Architects. The new plaza will include spaces for seating, gathering and learning. The new landscape will include trees, shrubs and perennials for year round interest, lighting and an architectural canopy with tables and chairs for creating and meeting.
- The Landscape Architects have completed the design development phase with construction scheduled for Summer. Attached are a few renderings of the design.
- Chimney scaffolding work in progress.
- Removal of the East Hall Plaza concrete slab is scheduled to begin at the end of September.
- It is anticipated to be noisy at times. We will work with the contractor to help minimize disruptions.
Site Access Plan
- The contractor continues work for demolition of the old boilers and mechanical piping in the Basement of East Hall.
- Sidewalk bridging will be installed in front of the East Hall Chapel as well as Chimney scaffolding in the next few weeks.
- Removal of the East Hall Plaza concrete slab is scheduled to begin as soon as all prep work is completed. It is anticipated to be noisy at times. We will work with the contractor to help minimize disruptions.
- 7/5 – Construction Trailer to Arrive
- 7/6 – 7/8 – Temporary Boiler Area Prep and 2nd Boiler Delivery
- 7/5 – Construction Trailer to Arrive
- 7/6 – 7/8 – Temporary Boiler Area Prep and 2nd Boiler Delivery
- Beginning mid-July – Installation of Construction Safety Fence Around Boiler Area. Installation of Construction Safety Fence to enclose Contractor Staging Area. Installation of Construction Safety Fence Around East Plaza. East Hall Entrance from Grand Ave Closed.
- Starting August 1st – Please be aware that Access into East Hall is restricted to Courtyard entrance only and from Main 2nd floor ramp. Grand Avenue west sidewalk closed from Chapel to South Walk. And North Walk closed between Grand Avenue and the Newman clock.
- Site Access Plan (Coming Soon)
Facilities Planning, Design + Construction
Summer 2022 Construction Project
Project: Boiler + Plaza + Chimney
Building: East Hall
Estimated Start: June 2022
Estimated Completion: Fall 2023
Starting as early as July work will begin on major upgrades to the central heating plant which provides the heating and hot water for most of the campus buildings. Work is scheduled to begin immediately after commencement and last for the next 18 months. Upgrades include removal of the old boilers and installation of new high efficiency boilers to replace them. The boilers are below East plaza which will need to be removed in order to access the plant below. Reconstruction of a new plaza will include landscape, outdoor furnishings and spaces for social interaction and an outdoor classroom. Included in this work will be repairs to the chimney and building façade. Access around East Hall and portions of Grand Avenue will be restricted to construction activities. This will necessitate alternative entrances to East Hall since the Grand Avenue doorway will be closed for most of the work.
We will be working with Pratt Communications on the messaging and signage to help keep everyone informed on the latest activities and up to date as the project progresses.
Several projects are set to begin including for Pratt Manhattan, Higgins Hall and Pantas Hall. In preparation of the facade work scaffolding will be installed around portions of the buildings. Please observe safety signage when accessing the building and be aware that some doorways may need to be closed temporarily.